AgriPulse Weekly Progress

Generated from git log
Sep 07 – Sep 12, 2026  ·  repo agripulse

A high-impact week focused on finalizing our data storage design review, hardening quality checks across three core systems, and resetting the delivery model from heavyweight documentation gates to building software one feature at a time. The new approach has passed independent review; formal owner sign-off is the next step before coding begins.

Turning Point: From Planning to Building

This week marked the most significant shift in project delivery since founding. Previously, every V1 feature contract had to be fully specified before writing a single line of code. The proposed new model lets us build and ship working software one feature at a time — dramatically shortening the path to a usable product. An independent reviewer confirmed the approach is sound. Formal owner approval is the next step; once recorded, the first feature can move into development.

At a Glance


15
Commits shipped
across 4 active days
3,699
Lines added
58 files touched
3
Conformance areas repaired
Identity · Storage · Workflow
1
Major delivery reset
build incrementally

Milestone Progress


This week the roadmap was fundamentally restructured. The old 101-stage planning sequence has been replaced with a clear three-part execution plan focused on delivering real buyer value. Progress is now tracked by milestones, each tied to a concrete user outcome.

Part 1 — Close the Transition (In Progress)

M0
Go

Milestone 0 — in progress: simplify the architecture for the first product, approve the new delivery model, and authorize the first feature

✓ Independent review passed (no blocking issues)  •  Owner sign-off pending  •  First feature authorization pending

Part 2 — Build the First Product Journey (After Part 1)

M1
M2
M3

Milestone 1: Search suppliers, review compliance evidence, start a procurement case  •  Milestone 2: Request and compare quotes  •  Milestone 3: Track samples through supplier selection

Part 3 — Validate with the Buyer (After Part 2)

M4

Milestone 4: Pilot with real authorized data in production

Key Delivery Change

The proposed governance amendment replaces the "finish all specifications before coding" rule with incremental authorization — each feature can be approved, built, and tested independently. It also simplifies the login system: instead of requiring enterprise corporate credentials (which can't exist before there's an app), the project will use modern passwordless authentication (passkeys) that works out of the box. Enterprise single sign-on remains available as an optional add-on for future corporate buyers. The amendment is proposed and has passed independent review; formal owner approval is the next step.

Key Highlights


Delivery Velocity


0 1 2 3 4 5 6 7 5 1 6 3 Mon 07 Wed 09 Thu 11 Fri 12
Monday wrapped up the storage admission review with 5 focused commits closing review gaps. Mid-week prepared the autonomous conformance candidate. Thursday was the highest-output day with 6 commits repairing conformance across identity, storage, and workflow systems while upgrading the developer tooling. Friday sealed the week with the governance resetβ€”revising AMD-2026-006, establishing the three-part execution plan, and locking storage boundary decisions.

Detailed Changelog


Hash Scope Description Area
Sunday, Sep 07 — 5 commits  ♦  Storage Admission Review Close
d98c2e2 architecture Repair storage admission review gaps—address outstanding issues in the journal storage and disaster recovery evaluation 3.4
a6c2563 architecture Close remaining storage review blockers to finalize the admission assessment 3.4
f3c0c4f architecture Record the official storage candidate review decision and evidence trail 3.4
346eadc repo Restore weekly report snapshot to maintain the historical progress record docs
6a26d95 architecture Complete the blocked storage admission evaluation—design-level review for FEAT-DATA-01 is finalized 3.4 eval
Wednesday, Sep 09 — 1 commit  ♦  Conformance Candidate Preparation
2c6f7cd repo Prepare autonomous conformance candidate—bundle existing contracts for cross-system verification quality
Thursday, Sep 11 — 6 commits  ♦  Conformance Repair & Tooling
9548c9e security Repair identity and authentication conformance gaps—strengthen session lifecycle, revocation, and privacy validation (402 lines improved) 3.3
4abec91 architecture Repair storage replay conformance gaps—expand journal replay fixtures and strengthen event schema validation (402 lines improved) 3.4
3386f56 workflow Repair procurement workflow and RFQ negotiation conformance gaps—align fixture schemas with domain contracts (621 lines touched) 3.5
f8910b4 repo Record conformance repair decisions and rationale in the project decision log docs
b84adc3 repo Clean up repository: add .gitignore rules for Python caches and local tooling runtimes repo
58c31e5 repo Configure Kubera Mode Context plugin—install Context7, Fallow, and token-hygiene protocols for AI engineering efficiency tooling
Friday, Sep 12 — 3 commits  ♦  Governance Reset & Execution Plan
69cbf73 governance Revise AMD-2026-006—replace the global pre-code gate with bounded-increment authorization, enabling feature-by-feature implementation policy
89f139a repo Add three-part execution plan to the roadmap with independent review and milestone structure roadmap
6e14d0b repo Define candidate ownership decisions and local storage boundary in normative architecture documents arch

Where We Stand


What's Next


Immediate — Milestone 0: Architecture Proportionality

  • M0 Resolve architecture proportionality choices. Review each existing architectural axiom (AX-01 through AX-19) for proportionality. Record concrete retain/simplify/defer decisions. Remove or simplify over-engineered contracts that don't serve the first buyer action.
  • M0 Authorize the first bounded increment. Admit, specify, and authorize the first implementation slice in existing records. This is the gate that unlocks actual software development.

Next — Milestone 1: Core Supplier View

  • M1 Build the first vertical buyer journey. Deliver working software for the core use case: a buyer views a supplier's compliance status and certificate evidence. This includes UI, persistence, and tests as a single vertical slice.

Then — Milestone 2: Buyer Workflow End-to-End

  • M2 Deliver the end-to-end procurement workflow. Extend the first slice to cover sourcing projects, RFQ creation, negotiation management, and case progression β€” validated with buyer feedback before expanding further.

Eight-Week Journey


Week Focus Changes Lines Milestone
Week 1 Project founding and blueprint 31 13,580 R-00 – R-04
Week 2 Data pipeline specification repair 6 16,780 R-05 – R-09
Week 3 External sources, governance, audit close 8 17,678 R-10 – R-12 ✓
Week 4 Architecture seams and baseline review 13 9,251 Stages 2.1–2.5 ✓
Week 5 Contract-drift repair and validation 7 7,498 Stage 2.6 evidence ✓
Week 6 Architecture approved, V1 scope mapped 9 1,238 Stage 3.1 ✓ · 3.2 candidate
Week 7 Infrastructure decisions locked, Security & Storage evaluated 10 1,564 Stage 3.2 ✓ · Stage 3.3 evaluated · 3.4 candidate
Week 8 Conformance repaired, delivery model reset 15 3,699 Stage 3.4 evaluated · Governance reset · Execution plan
Total (8 weeks) 99 71,288 Phase 2 ✓ · Phase 3 underway · Ready to build